Tile roof maintenance and waterproofing Completed in Lynnwood Pretoria

Introduction

A tile roof not sealed off properly will let water in. The consequences are that damp will accumulate inside the roof, mould will grow and timber will rot.

Description

This was a tile roof waterproofing (maintenance and waterproofing) out of the book. The concrete roof tiles were cracked and broke on critical spots letting water to penetrate. Ridge mortar filling between ridge tiles was separating and signs of mould growth showing. No flashing was found where the chimney and roof meats valleys were not sealed with waterproofing. This typical concrete tile roof needed waterproofing badly.


Tile roof
Tile joint not waterproofed

Missing tile and flashing not waterproofed
Missing tile and flashing not waterproofed

Problem/situation

The roof lacked proper tile roof waterproofing, In fact no waterproofing except for the prescribed plastic layer underneath tiles was previously applied. This led to water entering the roof which may in addition to dust which gathers in the openings, lead to mold growth and timber rotting.


Broken tiles
Broken tiles and joint not waterproofed

Mortar cracked and mold growth
Mortar cracking and mold growth

Possible outcome

With water entering the roof damp will form and stay inside for quite some time. Consequently mold will grow as well as the rotting of timber will occur. Needless to say that  it will lead to huge financial expenses to rectify. Then there is the medical expenses because of the unhygienic situation.

Suggestion to remedy the situation

Clean roof of all debris and dust with a high power hose. Replace all cracked and damaged tiles. Waterproof hips, valleys, ridges flashing and plungers vents. Paint with a high quality UV resistant paint.

Decision with customer/owner

An agreement with the owner was reached and work could commence.

Work done

First, the tile roof had to be cleaned of all debris and dust particles between tiles. All damage and cracked tiles were removed and replaced with new tiles. The valleys were carefully cut open and flashing as well as plumbers vents cleaned. Then the craftsmen waterproof all hips, valleys, ridges, flashing and plungers vents properly. A fresh coat of high-quality UV resistant paint finished the job.


Ridge, valleys and flashing waterproofed with membrane
Ridge, valleys and flashing waterproofed with membrane

Valley and joints waterproofed with membrane
Valley and joints waterproofed with membrane

Ridge,joints and flashing waterproofed with membrane
Ridge,joints and flashing waterproofed with membrane 

Result

The weather played its role and we had no rain during the contracting period. With all maintenance (roof repairs) done and tile roof waterproofing done. Adding a fresh coat of paint applied, this tile roof is good to go for years to come.


Flashing and valley painted after waterproofing
Flashing and valley painted after waterproofing



Tile roof painted after waterproofing
Tile roof painted after waterproofing

Tile roof waterproofing
Tile roof waterproofing

Outcome

With tile roof waterproofing done the property is ready to withstand rainfall and the occupants can rest assured that they will be protected against the weather.
Truly an excellent tile roof waterproofing contract well executed.

Tremco, we do it right! https://roofrepairs-pretoriaeast.co.za Call 0732708270